ECG Releases Another 22 Days ‘Dumsor’ Timetable

The Electricity Company of Ghana (ECG), has once again announced that parts of Accra will experience scheduled power outages for 22-days starting from Monday, June 28, 2021.

According to the power distributor, the outages would allow the Ghana Grid Company (GRIDCo) to complete the last phase of repair works on some bulk supply points and transmission cables in Accra.

The last phase of the repair and upgrade works, will see an upgrade in the Volta-Achimota-Mallam transmission lines.

The exercise will cause an interruption in power supply to some 71 communities within Accra.